Phases of Project management & calculations of parameters (CPM) :-
There Are three phases of the Project management:-
1. PLANNING :-
➤Dividing the project into distinct activities.
➤Estimating time requirement for each activity.
➤Establishing procedure relationship among the activities.
➤Construction of arrow diagram.
2. SCHEDULING :-
Determines the start & end time of each activity.
3. CONTROLLING :-
Uses the arrow diagram & time chart for continuous reporting.
PARAMETERS:-
(1) Earliest start time :-
Esj = Max ( Esi + Dij )
(2) Latest completion time :-
Lci = Min ( Lci - Dij )
(3) Total Floats :-
TFij = Lcj - Esi - Dij
(4) Free Floats :-
FFij = Esj - Esi - Dij
For more Detailing & understanding Click Here.
else
you can go to the
web.- https://drive.google.com/file/d/1a741oid9ZI_ozB1g3HoPfohO-TJlA4W6/view?usp=sharing
else
you can go to the
web.- https://drive.google.com/file/d/1a741oid9ZI_ozB1g3HoPfohO-TJlA4W6/view?usp=sharing
Thank you.
No comments:
Post a Comment
If you have any doubts let me know.